Licence number: 201
Title: Removal of Tertiary Pond from treatment process
Start date: 18 Oct 2019
 
Licence Condition
By 30 November 2021, the licensee must implement the recommended option/s outlined in the Bungendore Sewage Treatment Plant Options Report - Maturation Pond Bypass (Public Works Advisory, October 2020).
By 31 December 2021, the licensee must provide a report outlining completion of U1.1 above to the Manager Regional Operations, South East Region of NSW EPA.